Road Closures

Sarpy County

Giles Road, lane restriction near 144th Street

Starting Monday, there will be lane restrictions on Giles Road, lasting approximately three weeks. Giles will remain open in both directions the entire time.

ON MONDAY: From 10 a.m. to 3 p.m., the outside turn lane from Giles onto southbound 144th Street will be restricted. You will be able to turn onto 144th from the inside turn lane. Both turn lanes will be open during the morning and afternoon commutes. (See the first photo attached to this post.)

STARTING TUESDAY, lasting approximately three weeks: The eastbound lane of Giles will be restricted. Eastbound traffic will use the center turn lane. (See the second photo attached to this post.)

Please use caution when driving in this area.

Fort Crook Road, Capehart and Fairview roads

 There will be an extended closure of Fort Crook Road between Capehart Road and Fairview Road beginning Monday, March 26 at 9:00 a.m. for approximately two months, according to the Nebraska Department of Transportation.

This extended closure is necessary for the new alignment of Fort Crook Road between Capehart Road and Fairview Road.

Hawkins Construction Company of Omaha is the contractor on this project. Motorists are urged to drive cautiously through construction zones, along detours and selected alternate routes.

Contact:
Marvin Lech, P.E., 402-595-2534
District Construction Engineer

Fairview Road, 156th to 168th streets

Sarpy County Environmental Services, along with Lessard Contracting Incorporated, will close Fairview Road, between 156th and 168th, for landfill capping activities.  The closure will commence at 7:00 a.m. on Tuesday, March 14, 2017 and is scheduled to last until Saturday, September 30, 2017, weather permitting. The contractor is hauling fill material to the landfill cap over a portion of the roadway.

We are asking the traveling public to be aware of the closure and to find alternate routes of travel. Local traffic will be allowed to access all properties throughout the construction.

Pflug Road, Fishery Road to 228th Street

Beginning Wednesday May 31, 2017 @ 12:00 P.M., Sarpy County Public Works has closed Pflug Road from  Fishery Road to 228th Street to through traffic.  Erosion and slope stability issues have caused an emergent condition which required the roadway to be closed.  Project duration and corrective work is forthcoming.

Sarpy County Representative:  Patrick Dowse, PE, Engineering Manager: (402) 537-6917 (office).

We are requesting the traveling public be aware of the closure and to find alternate routes for travel.  Local traffic will be allowed to access all properties throughout the project.

132nd & Giles Intersection/Road Closures

UPDATE: Dec. 15, 2017

As of 11 a.m. on Dec. 15, 132nd Street is open in both directions. Giles Road is open east of 132nd Street.

Giles Road to the west of 132nd Street will remain closed until paving is complete. 

We appreciate the public's patience as this work continues.


Beginning Monday morning, July 17, 2017 at 9:00 a.m. Sarpy County Public Works will be closing the intersection of 132nd Street and Giles Road. The intersection will be closed in all directions for grading, utility relocations, placement of drainage pipes and paving.

Project Time: 75 working days (M-F), weather permitting.

Owner: Sarpy County, Bill Herr, Project Administrator (402) 537-6906.

Contractor: TAB Construction, Bill Ringsdorf (O) (402) 331-1244, Clint Holmes, (C) (402) 669-867Road Closure 132nd and Giles 07172017.pdf

Harrison Street, 154th to 156th

Beginning Monday, April 2, 2018, Harrison Street will close between 156th Street and 154th Street for Phase 1a of the Harrison Street Project. This is for the removal of the old pavement, grading, storm sewer, box culvert and paving.

The detour routes for this closure are using 156th Street north to Q Street and then east on Q Street to 144th Street; and south to Giles Road then east on Giles Road to 144th Street.

We are asking the traveling public to be aware of the closure and to find alternate routes of travel.

For updates for the project please visit the website: www.harrisonstreetproject.com.

Project Contractor:  John Gersivck, Vrana and Sons Construction, 402-306-4934

Project Representative: Bill Herr, Project Administrator, Sarpy County Public Works, 402-537-6906

156th Street, Harrison to Gertrude

Beginning Monday, April 23, 2018, 156th Street will close between Harrison Street and Gertrude Street for Phase 1B of the Harrison Street Project. The work will consist of removal of the old pavement, grading, storm sewer, and paving.

The detour route for eastbound Harrison Street for this phase of construction is 156th Street north to Q Street and then east on Q Street to 144th Street or 168th Street south to Giles Road, then east on Giles Road to 144th Street. The detour route for westbound Harrison Street for the remaining phases is 144th Street north to Q Street then west on Q Street to 168th Street or 144th Street to Giles Road then west on Giles Road to 168th Street.

The intersection of Harrison and 156th Street will remain open so the traveling public will be able to go north to Q Street.  Southbound traffic on 156th Street will need to travel to 168th Street, then south to Giles Road, then east on Giles Road to 144th Street.

We are asking the traveling public to be aware of the closure and to find alternate routes of travel.

For updates on the project, please visit the website: www.harrisonstreetproject.com.

Project Contractor: John Gjersvick, Vrana and Sons Construction Company
Phone: 402-306-4934                                        

Project Representative: Bill Herr, Project Administrator, Sarpy County Public Works
Phone Number:  402-537-6906

Let us help you with any of your questions regarding the Sarpy County Public Works.